Hi Raj

 

The CC gets creditd twice. Once when the production orders operations are confirmed and second when production orders are reevaluated after calculating actual activity prices

 

Logic is cost center provides services for producing the products. Hence it is credited when production orders are confirmed from co11n. This credit happens at plan price of act type in kp26. Once you calculate actual price and revaluae orders from con2, cc is credited again for any difference between plan n actual price. After this cc balance becomes zero

 

Note that CC is not credited during pgi. Cogs does not post to CC. It posts to copa

 

 